Sunshine North, Victoria

The project involved:

  • civil earthworks 11,500BCM in rock
  • subgrade supply and install using recycled crushed rock 500mm deep
  • stormwater and subsoil drainage
  • electrical and signalling conduiting
  • construction of 2no crane pads each 245m in length
  • Pavement construction and asphalt surfacing
  • Bottom ballast installation

Works were undertaken during the winter months over a period of 20 weeks.

Project Details

DATE

September 14th, 2012

 

CLIENT

McIntyre Rail Terminal

PROJECT TYPE

Industrial